MARTA GIRDER REPAIRS, NORTH TRAIN LINE, ATLANTA, GA

Repairs to Girders along North train line. Video inspection and repair of damaged drain lines, scaffolding erection, installation of new culverts. 27 Girders.    Project Amount $130,000.00



BRIGHTER HORIZONS DAYCARE, 644 W. PEACHTREE ST, ATLANTA, GA

Concrete demolition, concrete installation of retaining walls, pier columns, play areas, sidewalks, flatwork, curbs and catwalks. Project Amount $150,000.00



CITY OF ATLANTA FIRE STATION #13 AND #18

Exterior framing and installation of roofing systems. Interior installation of drop ceilings and gypsum walls. 

 Project Amount $40,000.00



EMPIRE STATE MIDTOWN PLAZA MALL, ROCHESTER, NEW YORK

Interior Demolition and asbestos removal of B-Foreman building located inside Midtown Plaza. 198,000 sq. ft.

Project Amount $ 1,069,000.00



CITY OF ATLANTA ELEVATED WATER TANK DEMOLITION, PITTS RD, ATLANTA, GA

Exterior demolition, excavation and site restoration of two (2) elevated water tanks. 2 million gallon multi-legged and 1 million gallon stand alone.   Project Amount $230,000.00



CITY OF ATLANTA DEPT. OF WATERSHED, 7680 BENWELL DRIVE, PUMP STATION

Interior demolition and asbestos removal, exterior demolition, above and underground utility removal, concrete excavation removal and site restoration.  Project Amount $70,000.00



CITY OF ATLANTA DEPT. OF WATERSHED, ADAMSVILLE ELEVATED WATER TANK

Interior waterproofing, sealing and painting. 5 million gallon stand alone elevated water tank. Exterior crack repair, sealing and painting exterior.   Project Amount $330,000.00